أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.
project must be completed by September1. The company plans to demo the new software product at a trade show in late September and therefore needs the project completed in time for the trade show. However, the sponsor has also told you that the budget is fixed at $,, and it would take an act of Congress to get it increased. You must complete the project within the given time frame and budget. Which of the following is the primary constraint for this project?
A. Budget
B. Time
C. Schedule
D. Scope
Answer: B
Explanation:
The primary constraint is time. Since the trade show demos depend on project completion and the trade show is in late September, the date cannot be moved. The budget is the secondary constraint in this example.