ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

Risk management allows the project manager and the project team to?

A.1)identify project risks, and2) . identify impacts of various risks, and3) plan suitable responses

B. identify project risks

C. plan suitable responses

D. identify impacts of various risks

E. eliminate most risks during the planning phase of the project

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC Manager , AL Bawani Contracting Co
تاريخ النشر: 2017/09/10
Aneesh Shandilya
من قبل Aneesh Shandilya , Manager/ Lead Electrical , Orpic

Thanks for the invitation, Option A is the correct answer.

SYED SHAIKH ABEL ALQUDSI
من قبل SYED SHAIKH ABEL ALQUDSI , Safety Manager , EMAS Marine Off-shore Services

Identify all risks anticipated and what mitigating or control measures to be taken to ensure safe and smooth execution of any project

Mohammad Hussein Aldweek
من قبل Mohammad Hussein Aldweek , General Manager , Invent Information Systems

Define hazards and associated risks then control it.

PRANTIK SARKAR
من قبل PRANTIK SARKAR , Construction Project Manager , Larsen & Toubro

E- it should be E , since from planning phase most of the risks shall be either eliminated or mitigated by introducing suitable action.

هل تحتاج لمساعدة في كتابة سيرة ذاتية تحتوي على الكلمات الدلالية التي يبحث عنها أصحاب العمل؟