Your mission-should you choose to accept it-is to complete the project using internal resources. The reason is that getting top-secret clearances for contractors takes quite a bit of time, and waiting for clearances would jeopardize the implementation date. Your programmers are percent of the way through the programming and testing work when your agency appoints a new executive director. Your programmers are siphoned off this project to work on the executive director's hot new project. Which of the following addresses the purpose of Scope Verification in this case?
A. Scope Verification documents the correctness of the work according to stakeholders' expectations.
B. Scope Verification determines whether the project results comply with quality standards.
C. Scope Verification determines the correctness and completion of all the work.
D. Scope Verification documents the level and degree of completion
Answer: D
Explanation:
Scope Verification should document the level and degree of completion of the project. If you come back at a later date and restart this project, Scope Verification will describe how far the project progressed and give you an idea of where to start.