أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.
system Which of the following statements is not true?
A. Work authorization systems are used throughout the Execution processes and are a tool and technique of the Direct and Manage Project Execution process.
B. Work authorization systems are written procedures defined by the organization.
C. Work authorization systems are used throughout the project Execution processes.
D. Work authorization systems clarify and initiate the work for each work package.
A. Work authorization systems are used throughout the Execution processes and are a tool and technique of the Direct and Manage Project Execution process.
Statement A does not appear to be true
Answer - A
this is an input to Monitoring & Controlling project work of M & C process group.
"A" is not true because Work Autthorization Systems is an input to Execution Process Group.
The option "A" is not true
option" A" is not a true statement
Option A is not True statements -- Work Authorization system is not a tool or technique to direct and Manage the project execution.
B. Work authorization system are written proceedures defined by the organization.
the answer is : statement (A) is not true