You are the project manager for Design Your Web Site, Inc. Your company is designing the website for a national grocery store chain. You have?

your activity list in hand and are ready to diagram the activity dependencies using the PDM technique. Which of the following statements is true?

A. PDM is also the AOA diagramming method.

B. PDM is also the AON diagramming method.

C. PDM is also the AND diagramming method.

D. PDM is also the ADM diagramming method

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2017/09/30
Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: B

Explanation:

The precedence diagramming method is also known as the activity on node (AON) diagramming method.