your activity list in hand and are ready to diagram the activity dependencies using the PDM technique. Which of the following statements is true?
A. PDM is also the AOA diagramming method.
B. PDM is also the AON diagramming method.
C. PDM is also the AND diagramming method.
D. PDM is also the ADM diagramming method
Answer: B
Explanation:
The precedence diagramming method is also known as the activity on node (AON) diagramming method.