A. Control Costs process
B. None of the other alternatives apply
C. Estimate Costs process
D. Determine Budget process
Answer: C
Explanation:
Cost management plan: Describes how cost variances will be managed and Part of the overall project plan. Output of Estimate Costs process is: Cost estimates and Cost management plan