ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

Your nonprofit organization is preparing to host its first annual 5K run/walk in City Park. You worked on a similar project for the organization two?

 years ago when it cohosted theK run through Overland Pass. Which of the organizational process assets might be helpful to you on your new project?

A. The project SOW, which describes the high-level details of the run/walk program

B. The strategic plan, because you'll want to make sure the project reflects the overall strategic

direction of the organization

C. Historical information on theK run project

D. The organization's PMIS system

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2017/09/30
Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: C

Explanation:

Historical information on projects of a similar nature can be helpful when initiating new projects.

They can help in formulating project deliverables and identifying constraints and assumptions and

will be helpful later in the project Planning processes as well.