أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.
years ago when it cohosted theK run through Overland Pass. Which of the organizational process assets might be helpful to you on your new project?
A. The project SOW, which describes the high-level details of the run/walk program
B. The strategic plan, because you'll want to make sure the project reflects the overall strategic
direction of the organization
C. Historical information on theK run project
D. The organization's PMIS system
Answer: C
Explanation:
Historical information on projects of a similar nature can be helpful when initiating new projects.
They can help in formulating project deliverables and identifying constraints and assumptions and
will be helpful later in the project Planning processes as well.