Which is not correct about initial phase of a project?

A. The highest uncertainty is at this stage of the project.

B. The cost associated at the initial phase of the project is highest.

C. All of the other alternatives apply

D. Stake holders have maximum influence during this phase

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2017/10/07
Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: B

Explanation:

minimum cost at the project initiation stage because minimum requirement of resources .