You are a project manager for Bluebird Technologies. Bluebird writes custom billing applications for several industries. A schedule change has been?

requested. You know change is concerned with all of the following except which one?

A. Determining that a change occurred

B. Influencing causes of change

C. Verifying change

D. Managing change

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2017/10/13
Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: C

Explanation: Integrated Change Control, Schedule Control, and Cost Control are all concerned with three issues: influencing the things that cause change, determining that change is needed or has happened, and managing the change.