You are a project manager for Dakota Software Consulting Services. You're working with a major retailer that offers its products through?

 mail-order catalogs.The company is interested in knowing customer characteristics, the amounts of first-time orders, and similar information. As a potential bidder for this project, you worked on the RFP response and submitted the proposal. When the selection committee received the RFP responses from all the vendors bidding on this project, it used a weighted system to make a selection. Which process did this occur in?

A. Request Seller Responses

B. Select Sellers

C. Plan Contracting and Purchases

D. Contract Administration

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2017/10/13
Mohammed Awad
من قبل Mohammed Awad , Regional Supply Chain & Operations Director , Tamakkon Co.

I would take B as an answer to your question.

يوسف دمدوم
من قبل يوسف دمدوم , مهندس و مسير , مقاولة اشغال البناء

thank you for the invitation

I agree the option B

Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: B

Explanation: Select Sellers involves the receipt of bids and proposals. Weighted systems are one of the tools and techniques of this process used to evaluate vendors based on selection criteria defined by the organization.