You performed this project under contract. You are in the Contract Closure process and know that you should document which of the following? (Choose the best response.)
A. Formal acceptance
B. Administrative closure procedures
C. Contract closure procedures
D. Product verification
Answer: A
Explanation: The project manager is responsible for documenting the formal acceptance of the work of the contract. This should be done during Contract Closure when projects are performed under contract or during Close Project if no work was performed under contract. In cases where part of the work was performed under contract and part with in-house staff, formal acceptance should occur in both of these processes.