You are the project manager for Lucky Stars nightclubs. They specialize in live country and western band performances. Your newest project is in the?

Planning processes group. You are working on the WBS. The finance manager has given you a numbering system to assign to the WBS. Which of the following is true?

A. The numbering system is a unique identifier known as the code of accounts, which is used to track time and resource assignments for individual work elements.

B. The numbering system is a unique identifier known as the WBS dictionary, which is used to assign quality control codes to the individual work elements.

C. The numbering system is a unique identifier known as the code of accounts, which is used to track the costs of the WBS elements.

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2017/11/03
يوسف دمدوم
من قبل يوسف دمدوم , مهندس و مسير , مقاولة اشغال البناء

Thank you for the invitation

I agree the option C

Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: C

Explanation: Each element in the WBS is assigned a unique identifier. These are collectively known as the code of accounts. Typically, these codes are associated with a corporate chart of accounts and are used to track the costs of the individual work elements in the WBS.