ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

This process uses tools like decomposition and rolling-wave planning to produce the activity list and other?

outputs. Because of the purpose of this process, which of the following is considered its primary input?

A. WBS

B. Constraints and assumptions

C. Project management plan

D. PMIS (as part of enterprise environmental factors)

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2017/11/09
Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: AExplanation: This question is describing the Activity Definition process. The purpose of this project is to decompose the work package elements of the WBS into activities. The WBS is the primary input of this process.