ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

You are a project manager of ABC company. You have created the project charter and it is not approved from buyer?

 But your manager is forcing you to start the project right away. What is the BEST thing to do?

A. Start project right away.

B. Ask your manager to send approval email.

C. Start work on complex activities.

D. Do the impact analysis and show the impacts of start project without approval.

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2017/12/21
Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: DExplanation: The best thing to do the impact analysis and show the impacts of start project without approval. This is the only choice that prevents future problems .

المزيد من الأسئلة المماثلة