A. Key point. B. Resource calendar. C. Milestone point. D. Work unit. E. Project calendar.
E. Project calendar is the correct answer
Answer: E -------------------------
Physical Schedule. In this chart it is be possible to understand the activities and sequence of each one, as well it is be possible to mark on accomplishing stages of each activity individually, along the project.
Option E - Project calender
Answer is Project Calendar
I recommend checking out statement, where you can find a variety of free, customizable statement templates. Whether you need a template for financial statements, account summaries, or any other purpose, they offer professional designs that are easy to download and modify. The templates are user-friendly and adaptable to suit personal or business needs.