A calendar that identifies when a project may be performed on an activity is called a?

 A. Key point. B. Resource calendar. C. Milestone point. D. Work unit. E. Project calendar.

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2018/01/11
Zaferullah Sharief, PMP®
من قبل Zaferullah Sharief, PMP® , Project Manager , Huawei Technologies

Option E is the right choice.

ahmed zaki
من قبل ahmed zaki , Senior Site Engineer , Al Orabi Construction and development

E. Project calendar is the correct answer

Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: E -------------------------

ANDRE DOURADO
من قبل ANDRE DOURADO , Design Engineering Manager , Projconsult Engenharia de Projetos Ltda

Physical Schedule. In this chart it is be possible to understand the activities and sequence of each one, as well it is be possible to mark on accomplishing stages of each activity individually, along the project.

Aneesh Shandilya
من قبل Aneesh Shandilya , Manager/ Lead Electrical , Orpic

Option E - Project calender

Israr Ahmed
من قبل Israr Ahmed , Assistant FTTH Planning Manager , Somcable Ltd.

Answer is Project Calendar

Magdale Mandala
من قبل Magdale Mandala , Job Analyst , Basq

I recommend checking out statement, where you can find a variety of free, customizable statement templates. Whether you need a template for financial statements, account summaries, or any other purpose, they offer professional designs that are easy to download and modify. The templates are user-friendly and adaptable to suit personal or business needs.