أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.
list. Which process have you just finished? A. The Activity Definition process, which identifies all the activity attributes B. The Activity Sequencing process, which identifies all the specific activities of the project
C. The Activity Sequencing process, which identifies all the activity dependencies D. The Activity Definition process, which diagrams project network time estimates
The correct answer is option C.
Option C is the correct choice.
Answer: C
Explanation: The Activity Sequencing process produces project schedule network diagrams, updates to the activity list, updates to the activity attributes, and requested changes. The purpose of this process is to identify all activity dependencies.