A Gantt chart is useful in determining ?

A. The level of effort of a task B. When a task starts and stops C. How tasks are related to each other D. Who is assigned to what task E. All of the above.

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2018/01/18
Aneesh Shandilya
من قبل Aneesh Shandilya , Manager/ Lead Electrical , Orpic

Option B - Gantt chart is a type of bar chart that illustrates a project schedule. Gantt charts illustrate the start and finish dates of the terminal elements and summary elements of a project. Terminal elements and summary elements constitute the work breakdown structure of the project.

Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: BExplanation: Section: (none) Reference: Rita says that a Gantt chart in its purest form does not show task interdependencies. That would make B correct. (in second thought - According to PMBOK, Schedule development process - The Bar chart or Gantt chart, shows the durations, the starting and the ending date and sometimes the dependencies. So why would a and c not be an appropriate answer.)

Zaferullah Sharief, PMP®
من قبل Zaferullah Sharief, PMP® , Project Manager , Huawei Technologies

Option B is the best choice.

devansh  anand
من قبل devansh anand , IT Project Manager , Mahindra Ssg

adwjkhdkiauhksjdskdhbsmdnAd WDhjWD xhgAmsvcnmbdvsjhvszdjhzvdjzwhdvzjhdvzwdlkjhzvwdlhjzs cdkjdjkQWDjqdjqkdlqdmwewrrr 