ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

Management Contingency Reserve is identified in which process?

 A. Determine Budget B. Estimate Costs C. Estimate Activity Durations D. Estimate Activity Resources

 

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2018/01/24
Shaikh Subahan
من قبل Shaikh Subahan , PMO & DEV-OPS SUPPORT , Etisalat Telecommunications

It will come under Cost Management Process so the option B. Estimate Cost is the correct option.

Zaferullah Sharief, PMP®
من قبل Zaferullah Sharief, PMP® , Project Manager , Huawei Technologies

Option B is the correct choice.

Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: BExplanation: The difference between the Cost Baseline and Funding requirement at Project completion is Management Contingency Reserve. Management Contingency Reserve is identified in Estimate Costs process.

المزيد من الأسئلة المماثلة