change control system. You know all of thefollowing statements are true regarding Cost Control except for which one? A. Changes are reflected in the cost baseline. B. Performance is monitored to detect variances. C. Changes are monitored and reflected in the project scope. D. Changes are monitored so that inappropriate changes do not get into the cost baseline.
Changes are monitored and reflected in the project scope.
Option C is the best choice.
Answer: CExplanation: Cost Control tracks project performance to detect variances and reflect them in the cost baseline. It's also used to prevent inappropriate changes from getting into the cost baseline.