ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

You are a project manager for Laurel's Theater Productions. Your new project is coming in over budget and requires a cost change through the cost?

change control system. You know all of thefollowing statements are true regarding Cost Control except for which one? A. Changes are reflected in the cost baseline. B. Performance is monitored to detect variances. C. Changes are monitored and reflected in the project scope. D. Changes are monitored so that inappropriate changes do not get into the cost baseline.

 

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2018/01/24
RAJ DAHIYA
من قبل RAJ DAHIYA , Project Manager - Energy Optimization , Siemens

Changes are monitored and reflected in the project scope. 

Zaferullah Sharief, PMP®
من قبل Zaferullah Sharief, PMP® , Project Manager , Huawei Technologies

Option C is the best choice.

Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: CExplanation: Cost Control tracks project performance to detect variances and reflect them in the cost baseline. It's also used to prevent inappropriate changes from getting into the cost baseline.

المزيد من الأسئلة المماثلة