Certain resources have been added to tasks on the critical path so as to reduce the project duration. As a result the plan should then be reviewed?

for the:

 A. Possible lag time on other paths. B. Resource assigned to other tasks on the critical path. C. The most time consuming task remaining in the plan. D. Emergence of a new critical path.

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2018/02/14
Vipul Kumar
من قبل Vipul Kumar , Sr Rail Track Technologist , Free Lance Working

Whole project network needs to be reviewed every time there is alteration in the resources in any path, just being imperative incase the same is done to the critical path.

Alertness can be sustained through constant reviews only!

NABEEL TARIQ
من قبل NABEEL TARIQ , deputy general manager , The Residency Hotel

C. The most time consuming task remaining in the plan

Marlon Dreo
من قبل Marlon Dreo , Sr. Accounting Associate , DB Schenker

Audit and Quality assurance is indespensable task for any organization. It can reduce critical risk that might might create a big impact on cost and good standing of the project and even the entire organization. Review is very important than to do a root cause analysis.

VANNERI VENUGOPAL GOPALAKRISHNAN
من قبل VANNERI VENUGOPAL GOPALAKRISHNAN , Supply Chain Manager , M.H. Alshaya Co. W.L.L ( Al Shaya Group )

it would be advisable to revisit the strategy plan and review this over again

Falah Almutlaq
من قبل Falah Almutlaq , مدير مالي , جمعية شآبيب الخيرية لذوي الأحتياجات الخاصة

When there are numerous crticle ways in a venture, it implies, the venture has been separated into numerous stages. Extend director ought to guarantee opportune completion of different basic ways in arrange to total the extend on time.

Ryan Alaman
من قبل Ryan Alaman , Project Engineer/Mechanical Engineer , US Army Corps of Engineers

B. Resource assigned to other tasks on the critical path.

Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

D. Emergence of a new critical path.