 A. It is used to establish team members' availability to engage with the project. B. It is used to develop the work breakdown structure taking the available resources into account. C. It is to make certain that all team members comprehend what their roles entail. D. It provides a graphical representation of the project's organizational structure.

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2018/03/14
Zaferullah Sharief, PMP®
من قبل Zaferullah Sharief, PMP® , Project Manager , Huawei Technologies

Option C is the correct choice.

Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

C. It is to make certain that all team members comprehend what their roles entail.