Which of the following represents the BEST way to organize project activities for scheduling?

 A. By the critical path. B. By the task start date.

By the date of commencement of project. D. By work breakdown structure. E. By the responsible organization.

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2018/03/21
sheryll tarrayo
من قبل sheryll tarrayo , Beauty technicians , hala beauty center

in a project activities we should start by breakdown and activities then follow by the critical path and by the date of commencement of project then it goes to by the responsib;e organization

Nahyan Wahra
من قبل Nahyan Wahra , Accelerator Intern , Malaysian Global Innovation and Creativity Centre (MaGIC)

A - critical path

Usually, B and C can be found out when viewing the overall critical path of a project. D is basically details of the tasks and E the people responsible for delivering them. Therefore the critical path (A) is the best way to schedule project activities.

Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

D. By work breakdown structure.