What is necessary to check whether the scope of the project is being met?

 A. Omit problems from the conference report. B. Ensure that changes to the project character are reflected in the definition. C. Verify the project schedule is on track. D. Define causes and symptoms of identified problems. E. Conduct periodic inspections, reviews, and walk-throughs.

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2018/04/04
Loay AbdelRahman
من قبل Loay AbdelRahman , Business Development Officer (Non-Motor) , Al Shorafa Insurance Services

To set up a methodology that establishes the project's timeline, goals, and how to allocate resources. 

Jesus Zabala
من قبل Jesus Zabala , CIVIL SUPERVISOR , SOIMCA

Does not necessarily mean that the project is going well if meets the scope, to comply them but very elongated in time produces lost to the project, it is necessary to revise the labor force, and supervisor, run-times and the quality of the executed works, so that they do not produce re works that impact reaches in time and costs

Md. Imrul Hassan
من قبل Md. Imrul Hassan , UNITED ARAB EMIRATES AND BANGLADESH

After detail estimating including overhead within the scheduled time frame it is to be checked that the expected Profit can be achieved.

amir azam
من قبل amir azam , project consultant , Al- Moayyed Contracting Group

Verify the project schedule is on track

Muqeem Akhtar
من قبل Muqeem Akhtar , Sr. Project Control Engineer , Al Shoumoukh Group

B. Ensure that changes to the project character are reflected in the definition. Change orders or variation order or site instruction become the part of scope. So that should be tracked down carefully.

Kijjambu Micheal
من قبل Kijjambu Micheal , ICT officer , TECH SOLUTIONS

The correct stakeholders from the organisation commissioning the project must be involved very intimately at various stages of the project scope. When this does not occur, assumptions begin to be made (which are generally subjective) and stakeholder confusion can occur as the project goes on

فاطمة محمد الحافظ موسى
من قبل فاطمة محمد الحافظ موسى , محاضر متعاون , جامعة عمر المختار

The scope of the project consists of all the activities that are used (resources, human beings, funds), including quality standards, and includes

 

The goals of the legislator

Project limits

Project limitations

Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

E. Conduct periodic inspections, reviews, and walk-throughs.