Productivity in relation to Construction stems from the amount of work completed per laborer. I.e. Tiling Mason daily productivity could be5 square meters. Hypothetically, If you have to complete square meters of floor tiles with a deadline of days, you would plan to have tile masons working for9 days with1 day to fix any defects (Dependent on Project ITP, of course).
As such, Productivity rates and manpower/equipment histograms are imperative while planning for a Project.