ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

Which of the following is NOT a characteristic of the Project Management Plan?

A. Must be approved by project sponsor B. A bar chart that shows the order of tasks and their resource assignments C. Formal, written communication D. Collection of subsidiary plans

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC Manager , AL Bawani Contracting Co
تاريخ النشر: 2018/05/31
Maryann Karmon
من قبل Maryann Karmon

Which of the following is not a characteristic of a project A. An established objective B. Outcome is unique C. Continuous D. A clear beginning and end E. Never been done before

Abdullah Muhammad
من قبل Abdullah Muhammad , Civil Engineer , Royal Marvelous Swimming Pools and Landscaping L.L.C

I think option C is the answer, 

Muhammad Farooq
من قبل Muhammad Farooq , QA-QC Manager , AL Bawani Contracting Co

Answer: BExplanation: The Project Management Plan is not a bar chart (or a Gantt chart). It's the collection of all of the planning documents you create through all of the knowledge areas within the five process groups. It describes how your project will handle all of the activities associated with your project wor

المزيد من الأسئلة المماثلة

هل تحتاج لمساعدة في كتابة سيرة ذاتية تحتوي على الكلمات الدلالية التي يبحث عنها أصحاب العمل؟