A. Must be approved by project sponsor B. A bar chart that shows the order of tasks and their resource assignments C. Formal, written communication D. Collection of subsidiary plans
I think option C is the answer,
Answer: BExplanation: The Project Management Plan is not a bar chart (or a Gantt chart). It's the collection of all of the planning documents you create through all of the knowledge areas within the five process groups. It describes how your project will handle all of the activities associated with your project wor