You are planning a project that uses the same team as a project that is currently being performed by your company?

What should you consult to find information about when those people will be available for your project? A. The communications management plan for your project B. The project schedule for your project C. The staffing management plan for the project that the team is working on D. The project manager for the project that the team is working on

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2018/06/12
Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: CExplanation: The staffing management plan tells you everything that you need to know about when resources will be released from a project. Since the team you need for your project is currently on another project, that project's staffing management plan will tell you when they will be released from that project and available for yours.