A project manager is planning the staffing levels that will be needed through the course of her project. She figures out the number of people ?

that will be needed in each role over time and displays that information in a chart as part of her staffing management plan. What is that chart called? A. Resource histogram B. Gantt chart C. RACI matrix D. Organization chart

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2018/06/19
Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: AExplanation: A Resource histogram is just a way to visualize the number of people in each role that you will need on your project as time goes on. Once you have figured out your schedule and the order of activities, you figure out how many people it's going to take to do the work and plot that out over time. Then you have a good idea of what the staffing needs of your project will be.