Oe is a project manager on an industrial design project. He has found a pattern of defects occurring in all of his projects over?

the past few years and he thinks there might be a problem in the process his company is using that is causing it. He uses Ishikawa diagrams to come up with the root cause for this trend over projects so that he can make recommendations for process changes to avoid this problem in the future. What process is he doing? A. Qualitative Risk Analysis B. Perform Quality Assurance C. Perform Quality Control D. Perform Quality Planning

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2018/06/19
Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: BExplanation: Joe is doing root-cause analysis on process problems, that's Quality Assurance. Remember, Quality control is when you are trying to find problems in your work products through inspection. Quality Assurance is when you are looking at the way your process affects the quality of the work you are doing.

Khaled Rashad
من قبل Khaled Rashad , General manager , Ministry of International cooperation

C. Perform Quality Control