أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.
A. You must update the project management plan to reflect this change B. You must work with the team to document the lessons learned C. You must stop all work and release the team immediately D. You must keep the team working on the project to give your senior management time to talk to the client
You must work with the team to document the lessons learned
Answer: BExplanation: Even if a project is shut down before the work is completed, you still need to document the lessons learned and add them to the organizational process assets. In fact, if a project is terminated early, that's probably the best time to do that! When a project goes seriously wrong, then there are always important lessons that you can learn - even if it wasn't your fault!