ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

Your client has terminated your project before it is complete. Which of the following is true?

A. You must update the project management plan to reflect this change B. You must work with the team to document the lessons learned C. You must stop all work and release the team immediately D. You must keep the team working on the project to give your senior management time to talk to the client

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2018/06/27
Raed Hussein
من قبل Raed Hussein , Site Engineer , Gate Net Electronics

You must work with the team to document the lessons learned

Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: BExplanation: Even if a project is shut down before the work is completed, you still need to document the lessons learned and add them to the organizational process assets. In fact, if a project is terminated early, that's probably the best time to do that! When a project goes seriously wrong, then there are always important lessons that you can learn - even if it wasn't your fault!

المزيد من الأسئلة المماثلة