ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

Loay is the manager of a software project. His client has agreed on a Project Scope Statement at the beginning of the project, ?

but whenever the client verifies deliverables, he comes up with features that he would like to add into the product. Amit is working with the client to find what requirements were missed in the planning stages of the project and how to plan better in the future. What is the BEST description of his project's current situation? A. Schedule variance B. Gold plating C. Alternatives analysis D. Scope creep

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2018/07/26
Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Explanation: Answer: D

The project's scope is changing every time the client is asked to verify the product - that's scope creep. The best way to avoid that is to be sure that the Project Scope Statement that is written in the planning stages of the project is understood and agreed to by everyone on the project. Scope changes should never come late in the project; that's when they cost the most and will jeopardize the team's ability to deliver.

المزيد من الأسئلة المماثلة