A. Cost B. Quality C. Scope D. Time
It is Quality. Triple constraints are Scope, Schedule (Time) and Cost
Answer: BExplanation: Every project, regardless of what is being produced or who is doing the work, is affected by the triple constraint of time, scope, and cost. Any time you make a change to one or more of these constraints, it can also affect the other two - and the change can also affect quality, which is NOT one of the constraints. That's why you need to pay attention to all three constraints if you want your project to do well.