أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.
A. Project requirements B. Authorization for a project manager to work on a project C. Work packages decomposed into activities D. An initial set of schedule milestones
Work packages decomposed into activities is not typically found in a project charter since project have not been started.
Answer: CExplanation: The project charter is created long before you start identifying work packages and activities. Those things are done as part of the project planning, which only happens after the project charter is completed.