ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

Which of the following is not true about the Project Charter?

A. It formally assigns the project manager B. Includes a high level milestone schedule C. It is always created by the project manager D. It contains external constraints and assumptions

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2018/08/08
Jomar Depone
من قبل Jomar Depone , PROJECT MANAGER , R. DAN & CO., INC

Project Charter is not necessarily be done by the Project Manager but it identifies the level of authority of the Project Manager.

Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: CExplanation: The Project Charter is often created without the project manager's involvement. Sometimes it is handed to the Project Manager by the sponsor or high level manager.