At the beginning of the project, you hold a meeting with all of the stakeholders in your project in order to figure out how everyone will ?

communicate as the work goes on. Which of the following terms best describes that meeting? A. Qualitative Analysis B. Communication Plan meeting C. Kick-off meeting D. Status meeting

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2018/09/05
Muhammad Shah
من قبل Muhammad Shah , Communications Manager , Viral Concepts

Communication Plan meeting 

Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: CExplanation: The Kick-off meeting gets all of the stakeholders together to explain how communication will go. That way, everyone knows who to talk to if things go wrong or they run into any questions.