You are assigned as a project manager for an internal project. During cost planning and budgeting you found out, that there are peak times ?

of costs during the project and other times when costs are fairly low. What could this mean for the project? A. You may find another project manager with a project which has a different rhythm of high and low costs. Then, you may be able to move budget during one project's low cost periods to the other project. B. You are a project manager and work with a lifecycle budget for your project. Fiscal budgets are a matter of the functional organization, and you have generally not to care about them. C. You can silently create budget contingencies during low-cost periods and re-use them later during those periods when you have to cover peak levels in project costs. D. The fiscal budget mechanism which is used by the performing organization may not allow for cost peaks in your project, and you may have to smooth expenditures over time.

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2018/11/07
Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

D. The fiscal budget mechanism which is used by the performing organization may not allow for cost peaks in your project, and you may have to smooth expenditures over time.