A project manager is reviewing the scope of the project and the scope baseline of the project. This includes which of the following?

a. The original project schedule, budget, and scope b. The original project description and project charter c. The original scope of the project plus or minus any scope changes d. The current budget of the project

user-image
تم إضافة السؤال من قبل Zakir Muhammed , Contract Administrator , DS Contracting Co.
تاريخ النشر: 2018/12/26
Mohammed Qaisar I PMP I MCIPS I MBA
من قبل Mohammed Qaisar I PMP I MCIPS I MBA , Group Procurement Manager (Civil) , Al Ghurair Construction LLC

The original scope of the project plus or minus any scope changes during the execution of work.

Zakir Muhammed
من قبل Zakir Muhammed , Contract Administrator , DS Contracting Co.

ANS C - The original scope of the project plus or minus any scope changes.