when constructing the project schedule B. The CCM focuses on managing the total float of network paths to ensure that project are delivered on schedule C. The critical chain describes longest path through a project schedule network after resource leveling D. In CCM, planned activities are scheduled to their latest possible planned and start and finish dates
D. In CCM, planned activities are scheduled to their latest possible planned and start and finish dates
The Critical Chain Method has its roots in another one of Dr. Goldratt’s inventions: the Theory of Constraints (TOC). This project management method comes into force after the initial project schedule is prepared, which includes establishing task dependencies.
B. The CCM focuses on managing the total float of network paths to ensure that project are delivered on schedule