A. Approved change requests B. Supporting schedule C. Procurement audit documentation D. Warranties E. Payment records
Correct Answer is C.: Procurement audit documentation
E. Payment records
The buyer must have accepted the deliverables and agreed that they were delivered as promised withinthe contract. Also, the buyer must have completed the financial obligations on his end. All payments, including any finalpost-deliverable payment, must have been received by the seller, before a contract can officially be considered closed.
C. Procurement audit documentation