Which of the following is the total amount of time that a scheduled activity may be delayed from its early start date without ?

delaying the project finish date? A. Critical float B. None of the choices are correct C. Average float D. Total float E. Free float

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2019/04/11
Sawyer Lost
من قبل Sawyer Lost , Ex. Head of human resources , Srilank

Thank you for providing this information. I'm currently depressed and want to try my luck on this dating website flirtymature website review What are your thoughts on this concept? I'd like to hear your views on this as well, so please email me a few lines. I'll be patient.

Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

D. Total float ----------------