Which of the following BEST describes the procedures by which the project schedule can change, and includes the paperwork, ?

tracking systems, and approval levels necessary for authorizing changes? A. Schedule change control system B. Integrated change control C. None of the statements are correct D. Configuration management system E. Schedule comparison bar charts

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2019/04/11
Hayat Mansour
من قبل Hayat Mansour , Program Planning and Control Manager , MVL Group

A. Control Change schedule process which comparing the actual schedule with the schedule baseline to determine the variations and also to determine what corrective actions require, to get the project on track, and Paperwork we call it as "project document updates" and it is one from the output of the Control Schedule Process

Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

A. Schedule change control system 