You are the project manger assigned to build the house. You have determined the dependencies between activities on the project. ?

One of the activity dependencies is that the foundation of the house must be created prior to the construction of the frame which of the following is true? A. This is start-to-finish relationship B. This is an example of mandatory dependency C. This is an example of preferential logic D. This is start-to-start relationship E. This is finish-to-finish relationship

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2019/04/17
Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

B. This is an example of mandatory dependency 