أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.
a financial consulting company, to develop a comprehensive workstation offering real-time advanced charting, decision support tools, and portfolio management. The terms and conditions of the contract explicitly stipulate that XY Corp must provide weekly status reports and performance reports regarding the project work. However, the seller has failed to provide any status report for the past3 weeks. Which of the following is the BEST action to take? A. Issue a change order B. Issue a letter of default C. Issue a stop work order to XYZ Corp, until the missing status reports are prepared D. Alert the management team E. Half payments until the missing status reports are prepared
B. Issue a letter of default -------------