You are the project manager for the software company that develops stock analysis software. You have been assigned to develop ?

a new technical analysis tools to forecast the price of stock given its historical volatility based on Elliot Wave techniques. You need to gather necessary information to write the project scope management plan. Which of the following tools/ techniques will NOT be useful for you in this process? A. Forms B. Templates C. Project management plan D. Expert judgment E. Standards

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2019/05/01
Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

C. Project management plan ---------------------