so that its customer can pay bills online. You are ready to begin the activity duration estimates for your project. Two years ago you were involved in prior project where a team of ten programmers were able to create similar bill pay software in days. Therefore in estimating the duration of this new project, you decided to use days as an estimate. This is an example of which type of estimating technique? A. Qualitatively based duration B. Analogous estimating C. Reserve time D. Decomposition
Online Payment - Accept payment from anywhere, Fraud and Risk Management, Online pay gate way, Real Time Dash Board , Zero Security Deposit, Build IT with speedy integeration - Reserve Time
B. Analogous estimating -------------------