أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.
A. Efficiency indicator to reflect cost performance of project B. Value of the work completed C. Portion of approved cost estimate planned to be spent D. Efficiency indicator to reflect schedule performance of project E. Total of costs incurred in performing work activity
The answer is Option A. However Option D is the resultant of the EV analysis against the Plan.
B. Value of the work completed --------------