You have been recently hired to be a project manager at a bio-tech company to develop a new drug to treat pancreatic cancer. ?

The drug has been under development and clinical testing for past5 years. The FDA is currently reviewing the clinical data in order to determine weather the drug has any serious side effects. If the FDA does NOT approve the drug, the project will be in trouble. This is an example of which type of risks? A. Fore majeure risk B. Internal risk C. Organizational risk D. External risk E. Project management risk

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2019/05/30
Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

D. External risk -----------------