أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.
All of the following are tools/ techniques you can use EXCEPT: A. Estimating duration by multiplying the quantity of work to be performed by productivity rate B. Estimating duration by calculating the average of three duration estimates (most likely, optimistic, pessimistic) C. Estimating duration by calculating multiple project durations with varying sets of activity assumptions using Monte Carlo analysis D. Estimating duration by using contingency reserves E. Estimating duration from a previous, similar schedule activity based on historical information and expert judgment
C. Estimating duration by calculating multiple project durations with varying sets of activity assumptions usingMonte Carlo analysis