1. The schedule covers the whole of the scope2. The schedule satisfies the contract with the dates, durations and milestones3. The hard logic satisfies the schedule If this is correct then please add your experience and observation for the juniors in this forum
It seems easy, but these consditions are not easy to satisfy. The Conslutant usually can find a way to reject the scheduele.