ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

What is the necessity of punch-list preparation?

Pre-commissioning equipment & system installation checking

user-image
تم إضافة السؤال من قبل Dipak Das Dipak , General Manager (M), Power , Tata Consulting Engineers Ltd
تاريخ النشر: 2014/01/21
Tomas Gimenez
من قبل Tomas Gimenez , Supervisor , Tepsi - Exterran

The necessity is to complete everything according to engineering, so with the preparation of a punch-list we have a document of what's missing, what's wrong and what we need to correct to have a ready for pre-commissioning and further a ready for commissioning.

Mudassar Bashir
من قبل Mudassar Bashir , Process Safety Engineer , Saudi Aramco Total Refining And Petrochemical Company - Satorp

A gap analysis tool that enable us to identify the difference in physical installation with that of design. Also help in safe execution, control on project execution time, quality of work and a best tool for the orientation and understanding of the people with the plant

Mohammed Ahmed Loghbi
من قبل Mohammed Ahmed Loghbi , Raw Material Administrator , Saudi Basic Industries Corporation (SABIC)

Final contractor payment is made when the punch list of items are completed to meet the project design required by the contract.

المزيد من الأسئلة المماثلة