Eg. In Project Buider, Cost is100,0 but when i check in CN41 transaction, reports showing different figure250,0 in WBS level but in activity it showing only100,0. How to troubleshoot this?
Thanks for your reply Mr.Joefil, i mean here only budget not actuals. I have assigned one activity (A) under WBS-01, considered the Budgetted cost for the activty in Project Cost Plan as100 bucks and please note that WBS-01 has only one activity. But when i see reports thru CN41/ CN41N, this WBS-01 cost showing more than i have considered in Project Cost Plan so i check the breakdown of the WBS in the same report which shows only one activity and the cost is correct but varying in WBS. Seems this is an error.
i think that WBS cost of250 is your budget, and you used only100 of it (in an Activity), that's why when you generate a cost report in CN41 it shows that way. -- based from your description.